Amazon Backs a 960 MW Nuclear Project at an Indiana Coal Site

Amazon, AEP and X-energy will study 12 small modular reactors at a former coal plant, targeting 960 MW for the grid and data centers. The agreement is large, but licensing and first-of-a-kind execution remain decisive.
Amazon is funding development of a proposed 960-megawatt nuclear plant at a former coal site near Terre Haute, Indiana, and would become its first power customer if the project is built.
American Electric Power would operate the facility, while X-energy would supply 12 Xe-100 small modular reactors. The companies say the electricity would serve the regional grid as well as Amazon data centers. The project is three times the size of the first commercial agreement Amazon and X-energy announced two years ago.
The scale is significant: 960 MW is roughly enough carbon-free power for more than 700,000 homes, according to Amazon. The company and X-energy have a broader ambition to deploy 5 GW of nuclear capacity in the United States by 2039.
The word "proposed" carries most of the risk. Small modular reactors are designed to lower cost through repeat manufacturing, but the U.S. industry has limited operating evidence at commercial scale. X-energy has not yet broken ground on its first planned plant at Dow's Seadrift chemical site in Texas, where its construction permit remains under Nuclear Regulatory Commission review.
AEP's grid connection gives the Indiana project a different structure from an isolated data-center plant. It could spread benefits and costs across a utility system, though the eventual rate treatment, capital responsibility and construction timetable are not yet settled.
For Amazon, the agreement expands its options for meeting electricity demand without relying entirely on gas or intermittent renewables. For investors, the milestones are regulatory approval, a final investment decision, financing and completion of X-energy's first project. Until those arrive, the 960 MW figure is a development target, not operating capacity.
Continue your AEP research
Related News
Amazon's 47% AWS Growth Forecast Raises the Stakes for AI Spending
Morgan Stanley's bullish Amazon call rests on faster AWS growth, rising cloud margins and heavy infrastructure investment. A separate nuclear agreement shows how urgently Amazon is trying to secure power for that expansion.
Microsoft's Maia 300 Is an Efficiency Bet, Not an Nvidia Exit
Microsoft says Maia 300 will deliver 40% more tokens per megawatt than leading GPU systems and scale in 2027, but the company is still operating a mixed-chip cloud.
Adobe's AI Usage Is Growing Faster Than Its Backlog
Adobe delivered 13% reported revenue growth and more than 150% growth in AI-first ARR, but remaining performance obligations rose only 8%, keeping monetization under scrutiny.
Gartner's Neocloud Warning Puts Financing, Not Demand, at Center Stage
Gartner expects more than 80% of neocloud providers to lose independent status by 2030. The risk is a mismatch between heavy infrastructure spending and cash earned before chips age.
Rocket Lab's Iridium Deal Faces an FCC Competition Challenge
Ligado asked the FCC to scrutinize Rocket Lab's $8 billion Iridium acquisition, adding regulatory risk as investors also absorb a delay to the Neutron rocket.